BP Camp Project Phase1:
It one of the important and large projects as it represents a miniature city with all its services of a very high level, which includes:
-Earth works (ditch and berm) fence 4,000 m.l
-chain-link fence work 4,000 m.l
-Reinforced concrete fence work 4,000 m.l
-Earth works (cut & fill) 1,500,000 cu.m
-Earth works for roads 150,000 cu.m
-Water network UPVC pipes from 50mm to 400mm total of 25,000 m.l with pump stations, concrete tanks, RO unit with capacity 200 cu.m/day
-Irrigation network HDPE pipes from 50mm to 220mm with pump stations, steel tanks, valve chamber and accessories
-sewage network with sedimentation tank and manholes used UPVC pipes 110mm to 600mm total length of 12,000 m.l
-Rain water network with manholes used UPVC pipes from 200mm to 1,100mm total length 7,000 m.l
-Supply & erection of 5 diesel generators with total capacity of 6,250 Mva with synchronization
-Supply & erection electrical power and lighting control panels
-Supply & erection cables in different sizes with total length 128,000 m.l for power, 40,000 m.l for lighting and 360,000 m.l landscaping lighting
– Electrical poles and fixture in different sizes no. 2,700
-Landscaping works includes interlock works 200,000 sq.m, grass 200,000 sq.m, trees different types no.30,000, flowers no.150,000 and palms no. 80
-Firefighting system
-Fire alarm system total wiring of 320,000 m.l with addressable panels
-CCTV system, PA system, fiber optics and internet
-ELV network used UPVC 48,000 m.l 110mm dia. With concrete manholes
-Administrative buildings caravan 18,500 sq.m
-Services buildings & warehouses 15,000 sq.m
-Residential buildings 15,000 sq.m
-Petrol station, wash station
-Roads works with gates
-Sewages treatment plant 80 cu.m/day with steel tanks